Off-plan buyers in Dubai are told that their money goes into an escrow account. That is true, and it is a real protection. It is also narrower than many assume, and it only works if you pay the right way and check the project yourself.
Below: what the law says, where it stops, and how to check a project before each payment. For the basics, see our guide to off-plan property in Dubai.
What does Dubai's escrow law require from developers?
The rule comes from Law No. (8) of 2007 Concerning Escrow Accounts for Real Estate Development in the Emirate of Dubai, issued on 6 May 2007. It applies to developers who sell units off-plan and receive payments from purchasers or financers towards those units.
Under Article 9, the escrow account is opened in the name of the project and is dedicated exclusively to building that project, and each project must have a separate account. The same article says no attachment may be imposed on the payments deposited in it, so the developer's other creditors cannot freeze that money.
Article 13 adds that if a developer mortgages the project to borrow money, the loan amount must also be deposited in the escrow account. Article 14 makes the escrow agent retain 5% of the total value of the account once the developer obtains the completion certificate, and release it only one year after the units are registered in the buyers' names. The DLD says the retention secures the repair of defects.
The escrow agent is a bank or financial institution licensed by the Central Bank of the UAE and approved by the Real Estate Regulatory Agency (RERA), according to the DLD's frequently asked questions. The account is opened only after RERA approves the project.
The text of Law No. (8) of 2007 published on the Dubai Legal Portal lists no amendment to it. The rules on cancellation and buyer default sit in a companion law, Law No. (13) of 2008 on the Interim Real Property Register. Its Article 11 was rewritten in 2009, 2017 and 2020, and its implementing bylaw, Executive Council Resolution No. (6) of 2010, sets out the cancellation procedure.
What can a developer pay out of the escrow account?
According to the DLD, payments from an escrow account are only for the contractors, consultants and marketing of the project, and only 5% of total sales can be spent on marketing. Other developer expenses do not qualify.
The developer reports that a construction phase is complete, the account trustee's engineer visits the site to confirm it, and only then is the trustee authorised to pay out. Your instalment pays for the building you bought, in step with the work on site.
The law backs this with penalties. Article 16 sets imprisonment, a fine of at least AED 100,000, or both, for offences such as appropriating project money or knowingly selling units in fraudulent projects. Article 17 strikes a developer off the register if it fails, without an acceptable reason, to start construction within six months of receiving permission to sell off-plan.
In 2024 Gulf News reported that the DLD fined three developers AED 500,000 each for promoting off-plan projects without completing the required registration procedures.
What does escrow not protect you from?
Escrow controls where the money goes, not how the purchase turns out. These risks sit outside it:
- Money paid anywhere other than the project's escrow account. The bylaw says a broker must deposit the sale price into the project escrow account and may not keep it in its own account or deduct its commission first.
- Money already properly spent on construction. If a project is cancelled, the DLD says the funds available are distributed to buyers in full or proportionally, depending on how much there is.
- A late handover. The escrow law has no compensation scheme for delay, so your remedies come from the sale agreement and the courts.
- The price you paid, resale values and rental demand.
How should you pay off-plan instalments in Dubai?
Pay only into the escrow account of the specific project named in your sale agreement and payment request. Because Article 9 requires the account to be opened in the name of the project, the account name should match the project, not only the developer's brand.
Under Article 11 of Resolution No. (6) of 2010, an off-plan sale made before the project is approved and registered with the DLD is null and void. Under Article 8, a developer may not charge buyers any amounts other than those the DLD approves.
For construction-linked plans, the DLD says that on receiving a payment request, the buyer has the right to know the current completion percentage through a letter from the project consultant approved by the DLD. Otherwise the buyer is not obliged to pay unless it is confirmed that the project has reached the stage set in the agreed schedule. A buyer can also obtain a completion report from RERA's technical auditor for a fee of AED 15,000 (about USD 4,084).
If the account details in a payment request differ from those in your contract, confirm with the developer and the DLD before you pay.
What happens if an off-plan project is cancelled?
RERA can cancel a project based on a reasoned technical report. Article 23 of the bylaw lists the grounds, including failure to start construction without valid justification, gross negligence and bankruptcy. The developer may file a grievance within seven working days, and RERA must decide within seven working days.
After cancellation, RERA asks the escrow agent to refund the amounts deposited in the escrow account to the people entitled to them within 14 days. If the escrow money is not enough, the developer must refund buyers within 60 days of the cancellation decision unless RERA extends that period. If it does not pay, RERA must act to protect buyers, including referring the matter to the courts.
The DLD says its liquidation section moves the funds into a DLD trust account and distributes them to eligible buyers. It calls the timeline indefinite: each project is handled in turn once all documents, amounts and eligible persons are available.
Under the current Article 11 of Law No. (13) of 2008, as rewritten by Law No. (19) of 2020, the developer must refund all payments made by buyers when RERA cancels the project by a final reasoned decision, or when work has not started for reasons beyond the developer's control and without its negligence. Under the 2017 version, the developer could keep up to 30% in that second case. Article 15 of the escrow law adds that if a project is not completed because of an emergency, the escrow agent must consult the DLD and either ensure completion or refund depositors.
What if the project is delayed or the buyer stops paying?
A delay on its own does not cancel a project, and the DLD says it cannot terminate a contract at the investor's request. A buyer who wants out of a project that has not been cancelled must go to the real estate court, where the DLD can only mediate.
The rules for a buyer who stops paying are in the same Article 11. The developer notifies the DLD, which serves a 30-day written notice on the buyer and tries to mediate a settlement. If that fails, the DLD issues a document confirming the completion percentage, calculated under RERA standards. The developer's options then depend on that figure:
| Completion confirmed by the DLD | What the developer may do | Refund of any excess to the buyer |
|---|---|---|
| Over 80% | Keep the contract and claim the balance, ask the DLD to sell the unit at auction, or terminate and keep up to 40% of the unit value | Within 1 year of termination or 60 days of resale, whichever is earlier |
| 60% to 80% | Terminate and keep up to 40% of the unit value | As above |
| Below 60%, work started | Terminate and keep up to 25% of the unit value | As above |
| Work not started, for reasons beyond the developer's control | Refund all payments (up to 30% could be kept under the 2017 text) | Under the procedures of Law No. (8) of 2007 |
The buyer can still go to court or arbitration.
How do you check a project and its escrow account?
The DLD's Project Status Enquiry service shows a project's completion percentage and details. It is available on the DLD website, in the Dubai REST app and through the DLD's WhatsApp channel. You enter the land number, project number or project name. The DLD lists no fee and says the result is immediate.
Gulf News quoted Ali Abdullah Al Ali, Director of the Real Estate Control Department at RERA, saying investors must verify through Dubai REST that off-plan projects are licensed and registered with an escrow account. A routine before each payment:
- Find the project by name or number and check that the developer and project match your sale agreement.
- Compare the completion percentage with the stage named in the developer's payment request.
- Check that the bank account in the request is the escrow account in the project's name, and pay only there.
- For a construction-linked instalment, ask for the consultant's completion letter before you pay.
- Make sure your contract is in the DLD's initial registration, which records off-plan sales, and keep every receipt.
See also the step by step guide to buying property in Dubai and the buyer questions page.
Sources
- Dubai Legal Portal: Law No. (8) of 2007 Concerning Escrow Accounts for Real Estate Development in the Emirate of Dubai (2007-05-06)
- Dubai Legal Portal: Law No. (9) of 2009 Amending Law No. (13) of 2008 (2009-04-12)
- Dubai Legal Portal: Law No. (19) of 2017 Amending Law No. (13) of 2008 Regulating the Interim Real Property Register (2017-10-18)
- Dubai Legal Portal: Law No. (19) of 2020 Amending Law No. (13) of 2008 Regulating the Interim Real Property Register (2020-11-24)
- Dubai Legal Portal: Executive Council Resolution No. (6) of 2010 Approving the Implementing Bylaw of Law No. (13) of 2008 (2010-02-14)
- Dubai Land Department: Frequently Asked Questions (2026-11-17)
- Dubai Land Department: Project Status Enquiry (2026-11-17)
- Gulf News: Dubai Land Department fines three developers Dh1.5m (2024-06-02)
General information, not legal, tax or financial advice. Rules change: check the current position with Malik or the official source before you act.